|
 |
Pilot Flexible Air Permit Profile
Source: Lasco
Bathware Corporation
Facility Type: Fiberglass reinforced plastic bathware
manufacturer
Location: Yelm,
Washington
The Olympic Air Pollution Control Authority (OAPCA)
and EPA worked with Lasco Bathware (Lasco) to develop a flexible
air permit that enables the company to make operational changes and
increase material utilization efficiency. To
achieve yield improvements and compete in an industry with short-term product
demand changes, the flexible permit ensures that Lasco has the ability
to rapidly change production lines and increase the capture of its input
materials on a per unit basis. The flexible permit also ensures that
all applicable regulatory requirements are addressed
and creates incentives for pollution prevention.
On June 7, 1997, Lasco’s facility in Yelm, Washington received
a flexible title V air operating permit (Permit No. 01-97) as part of EPA’s
Pollution Prevention Performance Partnership (P4) Program. Lasco
produces bath fixtures including fiberglass reinforced plastic bathtubs,
shower stalls, and whirlpools. The flexible permit contained minor
New Source Review (NSR) advanced approvals that enabled Lasco to add new
spray booths, change spray equipment, and change mechanical equipment in
a timely manner without triggering Major NSR. The flexible permit
ensured the best available pollution control technologies were installed
and that total air emissions remained under the approved plantwide emissions
limits.
Tools & Methods Used in the Pilot Permit
Advanced Approvals |
Approvals to make a range of operational changes within
several categories, such as adding new spray equipment and putty stations,
changing mechanical equipment, and changing the facility’s mold
conveyor system. |
Plantwide emissions caps |
Plantwide potential-to-emit (PTE) limit established
for VOC emissions (249 tons/year). |
Pollution prevention (P2) |
Source-specific BACT requirements on advanced-approved
changes. Because Lasco had previously engaged in P2 prior to the
flexible permit, the P2 program requirement formalized and broadened
Lasco’s ongoing efforts to reduce styrene. |
Approved replicable methodologies (ARMs) |
Enable Lasco to modify emission factors based on OAPCA-approved
source tests without re-opening the title V permit. |
Environmental Benefits and Pollution Prevention
- Reduced allowable and actual air emissions. Lasco had been actively
pursuing pollution prevention (P2) opportunities
prior to the flexible permit. The
P2 program requirement within the flexible permit
formalized and broadened Lasco’s ongoing efforts to reduce emissions. At
the outset of the flexible permit development process, it became clear
to both Lasco and OAPCA that the community had concerns, primarily associated
with styrene emissions and associated odor issues. Prior to and
soon after permit implementation, Lasco undertook a series of P2
initiatives that resulted in a 14% decrease in
emissions per unit of production.
- Easier P2 implementation. From 1996 to 2001,
Lasco estimates it has reduced VOC emissions
per unit by approximately 32%. Lasco
representatives reported that the flexible permit
made it more attractive for the facility to look for and implement P2
opportunities. In
addition to the P2 program requirements, Lasco
also voluntarily installed a regenerative thermal oxidizer (RTO) pollution
control device to accommodate pollution from a third line while remaining
below its potential to emit (PTE) cap. According to OAPCA representatives,
the measures undertaken by Lasco have reduced regional emissions for
bathware products since the local need for them would otherwise be met
by less efficient sources with more pollution emitted per unit of production. Lasco,
through P2, limited its emissions per unit of production
so as to allow greater overall production under
its emissions cap.
Economic Competitiveness Benefits
- Agile manufacturing. Lasco engaged in a series of advanced-approved
changes, including updating its emission factor and voluntarily installing
an RTO. These
actions combined to create head room under Lasco’s cap which then
enabled the company to increase production. In the past, managers
at the Yelm facility had been very averse to making changes that would
trigger permitting actions and they would wait to undertake changes until
the time of permit renewal, postponing implementation of some P2 opportunities. The
advanced approvals allowed Lasco to make a series of modifications that
created the opportunity to increase production from 126,045 units per year
(in 1997) to 132,548 units per year (in 2000) generating a significant
annual increase in profit. After the RTO was installed emissions
decreased per unit to 3.13 pounds per unit allowing production to increase
and reducing costs associated with styrene loss. The flexible permit
has enabled Lasco to shorten significantly the
time it needs to respond to a change in market demand or the emergence
of a process efficiency improvement opportunity.
Monitoring and Enforceability
- Replicable monitoring and routine reporting. During the course of
the flexible permit, Lasco conducted two stack tests to determine emissions
levels and to estimate future calculations of
emissions based on material usage. Lasco measures all VOC emissions, including fugitive emissions,
using an emission factor approach. The additional reporting and
monitoring required under the flexible permit assures enforceability
and results in additional data availability for both the permitting authority
and the public.
Government Efficiency
- Paperwork and backlog reduction. OAPCA representatives reported that
the flexible permit saved both the agency and
Lasco staff time associated with preparing and processing notice of construction
applications. During
the flexible permit, Lasco made five advanced-approved changes that would
have otherwise triggered case-by-case minor NSR permit actions. The
time savings also includes time spent drafting
a permit to construct, ensuring NAAQS compliance, modifying the title
V permit, and conducting the change-specific public review process.
Public Response
- Public support. When Lasco prepared their first title V permit application
in 1996, many residents in the Yelm community
did not view the company as a “good neighbor” due primarily to past odor issues. During
the permit development process, OAPCA therefore decided to surpass standard
title V public review and comment procedures by holding several public
information sessions to discuss the innovative flexibility and P2 provision’s
in Lasco’s draft permit. OAPCA was also proactive about
notifying participants of community meetings and associated information,
issuing fact sheets about the pilot permit project, releasing newsletters,
and improving communications between the facility, the local community,
and environmental agencies. During the title V hearing, no concerns
were voiced by the community with regard to the
draft permit.
For More Information
|